Mexico
EXPERIENCE
WE HAVE BEEN BUILDING THE BEST INFRASTRUCTURE
FOR MORE THAN 20 YEARS
PROJECT 103 SLT 704 BAJA CALIFORNIA
Engineering, procurement of materials and permanent installation equipments, training, construction and commissioning of the following works, located in the states of Sonora and Sinaloa:
- SE Culiacan Oriente Banco 1, 115 kV, two bays of line at 115 kV, one transformation bay at 115 kV, one three-phase transformer of 40 MVA and armored metallic boards at 15 kV.
- SE Cereso Banco 1, 115 kV, two bays of line at 115 kV, one transformation bay at 115 kV, one three-phase transformer of 40 MVA and armored metallic boards at 15 kV.
- LT Cereso Entq. Hermosillo Uno – Hermosillo Cinco, 115 kV-2c, TA.
- LT Culiacan Oriente Entq. Culiacan 2 – Culiacan 3, 115 Kv-2c, subterranean, insulated cable at 115 kV.
Ubicación: México, Sinaloa, Sonora
Fecha de inicio: September 10, 2004
Fecha de terminación: September 9, 2005
LT LEON III – LEON II. CONTRACT No. RRCE-051005
Construction of the civil and electromechanical works that includes the partial supply of the LT Leon III – Leon II, 115 kV – 2c – 12 km – 795 ACSR – Ta, located in the state of Guanajuato. Engineering, supply, construction, training and commissioning of 5 substations of 115 kV in the states of Nuevo Leon and Tamaulipas, Mexico.
Ubicación: México, Guanajuato
Fecha de inicio: December 21, 2005
Fecha de terminación: October 17, 2006
ELECTRICAL SUBSTATION. QUERETARO I. CONTRACT No. RRCE-051004
Construction of the civil and electromechanical works that include the partial supply of the S.E. Queretaro I Banco 2 Sustitucion 4AT-1F-75MVA-230/115KV-0/0 A, bank coming from the se Yautepec Potencia, located in the state of Queretaro.
Ubicación: México, Querétaro
Fecha de inicio: January 2, 2006
Fecha de terminación: October 17, 2006
SE SALAMANCA II. CONTRACT RRCE-051003
Construction of the civil and electromechanical work that includes the partial supply of the SE Salamanca II Banco 2, 4t-1f-75MVA-400/115KV-0/0 A, bank coming from the SE Puebla II, in the state of Guanajuato (includes the detail engineering for the foundations and metallic structures for the support of primary equipment, cable list and PC&M).
Ubicación: México, Guanajuato
Fecha de inicio: January 2, 2006
Fecha de terminación: May 25, 2007
PROJECT P1001
Engineering, training, supply and construction of the following works located in the states of Baja California and Sonora:
- Enlargement SE Nogales Aeropuerto (115 kV, 2 feeders), in Sonora.
- Enlargement SE Nogales Norte (115 kV – 2 feeders), in Sonora.
- LT 230 Kv Nogales Aeropuerto – Nogales Norte (230 kV, 25 km-l, 2c), in Sonora.
- SE Panamericana Fraccionamiento Bcos. 1 and 2, in Baja California.
- SE Parque Industrail San Luis, in Sonora.
- SE Presidente Juarez (115 kV, 12.7 km-l, 2c), in Baja California.
- LT Presidente Juarez-Panamericana Fraccionamiento 115 kV, 12.7 km-l, 2c, in Baja California.
- LT Parque Industrial San Luis Entq. Cerro Prieto I – Hidalog (230 kV, 25.5 km-l, 2c), in Sonora.
Ubicación: México, Sonora
Fecha de inicio:
Fecha de terminación:
SE JERONIMO ORTIZ. CONTRACT RRNE-061006
Engineering, partial supply and construction of the civil and electromechanical works of the SE Jeronimo Ortiz Martinez Bco. 3 + Mvar, located in the state of Durango, consisting of 2 feeders of 400 kV, one transformation bank of 3 At’s 400/230/13.8 kV of 100 MVA and 2 banks of power reactors of 400 kV.
Ubicación: México, Durango
Fecha de inicio: January 2, 2007
Fecha de terminación: March 31, 2008
SE LA TRINIDAD. CONTRACT RRNE-081007
Construction of the civil and electromechanical works of the SE La Trinidad, 5 feeders, 230 kV, located in the state of Durango (includes supply of outdoor equipments, engineering and training of the communications system).
Ubicación: México, Durango
Fecha de inicio: October 30, 2008
Fecha de terminación: August 31, 2009
PROJECT 42 LT RED ASOCIADA DE LA CENTRAL TAMAXUNCHALE. CONTRACT No. PIF-028/2004
Engineering, procurement of materials and permanent installation equipments, training, construction and commissioning of 3 (three) transmission lines with voltages of 400 kV and a total length of 397.1 km-c and 3 (three) substations with voltages of 400 and 230 kV, with a total capacity of 375 MVA, 233.3 MVAr of the inductive type and 12 (twelve) feeders, located in the states of Hidalgo, Queretaro and San Luis Potosi. Includes the following works:
- LT Las Mesas – Queretaro Potencia Maniobras: 400 kV, 2c, 196.8 km-l, 393.6 km-c; self-supported towers; conductor cable: ACSR/As 1113, 3 cond/phase; guard wire: 1 Alumoweld 7 No. 8 AWG +1 Opgw 36 fiber.
- LT Queretaro Pot. Maniobras Entq. Qro. Pot. – Tula Pv (L1 Y L2): 400 kV, 2c, 1.75 km-l, 3.5 km-c; self-supported towers; conductor cable: ACSR/As 1113, 3 cond/phase; guard wire: 1 Alumoweld 7 No. 8 AWG + 1 Opgw 36 fibers.
- SE Las Mesas + MVAr: 2 at 400 kV Intercon. Pee Tamazunchale; 2 at 400 kV LT Champayan (C1 + C2); 2 at 400 kV LT Queretaro Potencia Maniobras (C1 + C2); 7 X 33,33 MVAr LT Queretaro Pot. Man. (C1+ C2). Includes reserve reactor.
- SE Queretaro Potencia Maniobras: 2 at 400 kV LT Las Mesas (C1 + C2); 2 at 400 kV Apert. Qro. Pot.-Tula Pv (L1); 2 at 400 kV Aper. Qro. Pot.-Tula Pv (L2).
- SE Queretaro Potencia Banco 4: 3 At-1f-125 MVA-400/230 kV-0/0 A
Ubicación: México, Hidalgo, Querétaro, San Luis Potosí
Fecha de inicio: November 9, 2004
Fecha de terminación: October 24, 2006
PROJECT 50 LT 610 TRANSMISION NOROESTE – NORTE (2A FASE). CONTRACT No. PIF-026/2006
- LT Moctezuma – Nuevo Casas Grandes II (0-51 km-l, 164.8 km-c. Section 1 from SE Moctezuma Al km 0+510. 230 kV, 1c, self-supported towers, 0-51 km-l, 0.51 km-c, ACSR/As 1113 one conductor per phase; section 2 from km 0+510 to the SE Nuevo Casas Grandes II, 400 kV, initial operation 230 kV, 2c, existing self-supported towers, 0.00 km-l 164.29 km-c, ACSR/As 1113 two conductors per phase. Laying of the second circuit.
- SE Nacozari Mvar L1+L2 (neutral reactor for LT Nuevo Casas Grandes II (C1) and LT Nuevo Casas Grandes II (C2)).
- SE Moctezuma (1 at 230 kV LT Nuevo Casas Grandes II (C2)).
- SE Nuevo Casas Grandes II ampl. + Mvar (1 at 230 kV LT Moctezuma (C2) and one-phase reactors, 3 X 7 Mvar).
Ubicación: México, Sinaloa, Sonora
Fecha de inicio: December 8, 2006
Fecha de terminación: August 31, 2008
PROJECT 218 LT TRANSMISSION GRID ASSOCIATED TO THE PROJECT OF OPEN SEASON AND OAXACA II, III, IV (1A. FASE)
Engineering, procurement of materials and equipments of permanent installation, training, construction and commissioning of 2 transmission lines with voltage of 400 kV and a length of 424.2 km-c (LT Juile – Cerro de Oro 400 kV-154.28 km-c and LT La Ventosa – Juile 400 kV 270-6 km-c), and 3 substations with voltages of 400, 230 and 115 kV with a capacity of 2,125 MVA, 75 MVAr and 8 feeders (SE Cerro de Oro 400 kV, SE Juile + MVAr 400 kV and SE La Ventosa Bcos. 1, 2 and 3 400/230/115 kV). The titular of the Contract with CFE was constituted by ISOLUX, ELECTRICAS / EDEMTEC, PIDIRELYS (Electricas de Medellin/Edemtec has a participation of 21.02% on the project).
Ubicación: México, Oaxaca, Veracruz
Fecha de inicio: September 10, 2008
Fecha de terminación: October 4, 2010